Bac Lieu province is directing drastically in compensation and site clearance for the East North-South expressway project, passing through Bac Lieu province.
Clean premises will be handed over soon
According to a report on March 22 of the Housing and Land Fund Development Center of Bac Lieu province. Compensation and site clearance work for the component project of the Hau Giang - Ca Mau section of the East North-South expressway construction project (period 2021 - 2025) passing through Bac Lieu province Up to now, the measurement work has been basically completed 100%.
Currently, the consulting unit has completed the technical design documents, estimated relocation of power lines, optical cables, water pipes... The center has handed over 7.5/7.7km of ground (reaching 98%). .
The capital allocated in 2023 with the amount of 64.18 billion VND, disbursed 61.08 billion VND (reaching 95.1% of the plan).
According to Hong Dan District People's Committee, the project passes through Vinh Loc and Vinh Loc A communes, with 188 households affected. Up to now, 170 households have handed over the premises, and 15 households have not yet handed over the premises. 4 permanent houses have been built for about 2 years, so they cannot be relocated.
At the same time, there are some cases where the construction unit is outside the scope of land clearance. Hong Dan District People's Committee requested the Provincial Housing and Land Fund Development Center to measure and set up landmarks according to the scope of site clearance.
Up to now, contractors have built 6km, currently some households have not handed over the site due to compensation work.
Therefore, the My Thuan Project Management Board suggested that Bac Lieu province should establish a team to mobilize people to hand over the site and handle it in March 2023.
Set up a hotline, handle problems
In order to speed up the land clearance progress of the section through the province, Mr. Le Tan Can, Standing Vice Chairman of Bac Lieu Provincial People's Committee suggested: "In the coming time, it is necessary to pay attention to the coordination between the Housing Fund Development Center and the Housing Fund Development Center. provincial land, Hong Dan District People's Committee with construction units in landmark planting and construction".
Standing Vice Chairman of Bac Lieu Provincial People's Committee requested the Provincial Housing and Land Fund Development Center, when the site clearance is recovered, compensation should be calculated correctly, if any households cause difficulties, they will conduct construction protection.
It is requested that the My Thuan Project Management Board soon transfer 42 billion VND to timely compensate the households who have handed over the premises, but have not yet received the compensation.
Particularly, shrimp farming households are still reluctant to agree to hand over the premises for fear of affecting farmed shrimp, requesting the construction unit to study possible solutions, to avoid maximum impact on people's farmed shrimp.
Mr. Le Tan Can also suggested: “In the general spirit that Bac Lieu province will give drastic direction, the province will set up a hotline to receive and handle problems related to project construction, in order to ensure the project project is implemented on schedule”.