The Ministry of Transport requested the construction of rolling sections of the route with favorable conditions to increase the disbursement value of the North-South expressway through Quang Binh and Ha Tinh.
The Ministry of Transport has just issued a document directing the PMU 6 on the implementation of construction, quality management and progress of the
North-South expressways of Vung Ang-Bung and Bung-Van Ninh.
The Department of Transport is especially interested in disbursing capital for the project, requesting the PMU 6 to direct the contractors to focus on construction, quickly complete the roads with favorable conditions, and immediately start construction. foundation layer, road surface to increase disbursement value.
The text clearly states. “Contractors also need to focus and prioritize the implementation of projects with high output value (bridges, culverts, tunnels ...) and control cash flow (specialized spending accounts) to ensure financial resources for projects. judgment and comply with the provisions of the law".
Determining that the first phase of the project needs to deal with a very large amount of work, the Ministry of Transport proposed the PMU 6, the supervision consultant, the designer, and the contractor to mobilize enough personnel present at the scene to focus on the project. remove difficulties and obstacles, immediately construct the sites that have been handed over, convenient locations, positions that play a role in determining the progress of the project (soft soil treatment, public service roads, etc.) bridges, tunnels, etc.).
Regarding the construction schedule, the PMU 6, the supervision consultant, the contractor are required in March 2023 to complete the construction of the overall and detailed schedule.
The construction progress must be scientific and feasible on the basis of actual conditions, site clearance work, ability to supply supplies and materials, weather conditions, and capital disbursement plan. Monthly.
Regarding quality management, on the basis of field inspection, the Ministry of Transport noted that currently, some contractors have mobilized testing stations at the site. However, in order to put into operation, to ensure strict management of the quality of the work from the very beginning, the PMU 6, the supervision consultant, the contractor shall check and review the approval procedures; Mobilize additional human resources for testing according to the contract's provisions in order to meet the construction progress.
"With the supervision consulting force, currently having mobilized the office at the site, the PMU 6 must direct the inspection, review and arrange a sufficient number of resident consulting engineers at the construction site in accordance with regulations of the Government. contract", the document stated.